Resurface Baseball Field 3,000 Fall - 07
Replacing beds and mattress in the Kitchen/Staff Area

$350 per bed

Summer-06
Clean and Paint Dining Hall   Spring-06
2 trees removed from girls cabin area   Spring-06
Build 7 RV hookups (water and power) upgrade electrical panel   Spring -06
Rebuild 1/3 of girl's cabin 3         Rebuild of cabin 3   Spring -06
Pad under Clothesline $ 350  Fall - 05
Build french-drain to remove water from the Dining Hall $ 700  Spring- 05
 Removal of dead pines (Forest Service Requirement)/ rebuild Kitchen Porch  $ 1,350  Spring - 05
 Two new cement picnic tables - special donation  $  1,100  Spring - 05
 New stage for campfire  $  4,300  Spring - 05
 Replacement of Kitchen Floor  $11,500  Spring -04
 Replacement of Kitchen Equipment  $  7,500  Spring -04
 Finish re-roofing main building  $  6,000  Spring - 04
 Rebuilding of girls cabin 5  $  8,400  Spring - 03
 Waterline from Spring to Ball Field  (2.5 m ppt)  $  8,500  Fall - 03
 Re-plumbing girls and boys sinks/ Trailer Station/ Nurse's leach line   (9.9 m ppt)  $  1,500  Fall - 02
 Replacement of leach field with in field behind girls cabin area  $34,000  2000
 15 cabins re-roofed (15 year period) $ 16,000  1990-2005
 Canteen-log-cabin $ 22,000  1990-1991